We’ve been working through the existing soil conditions and building up Building Pad #1 in 8-inch lifts, with each stage being tested and verified by Geotech. We’re officially at subgrade and ready to start digging footers. The plan from here moves FAST: ➡️ Dig footers today/tomorrow ➡️ Prep rebar & chairs ➡️ Pour footers Wednesday ➡️ Mason right behind us laying block ➡️ Underground plumbing ➡️ Insulation ➡️ Pour the slab ➡️ START FRAMING 🔨 A lot of work happens underground before you ever see a building coming out of the ground. Getting the pad, compaction, elevations, and foundation right is where it all starts. Once we get these footers poured, MC Luxury Villas officially starts going vertical. 24 luxury units coming to Newark, Ohio. Development is all about solving problems daily, building it right, and keeping the project moving. #realestate #development #construction