During business continuity planning, the IT director assigns recovery time objectives based on system complexity and restoration effort. Several business units later dispute the recovery priorities. Who should the BCP coordinator ensure determines the RTOs? A. The IT director, who understands restoration capability B. Business process owners, based on impact analysis C. Executive management, to resolve the dispute with authority D. The BCP coordinator, to maintain plan consistency (Explain your answer for more points in the comments!) Come back for the answer tomorrow, or study more now!