I was involved in a project where the client required the schedule to pass the DCMA 14-Point Assessment. The checks are simple, and they make weak programmes easy to spot, very useful also for claims management: Missing logic under 5% No leads, and lags kept under 5% At least 90% finish-to-start relationships Hard constraints under 5% Activities and total float over 44 working days kept under 5% No invalid dates, and no negative float left unexplained Critical path test, CPLI and BEI to show whether the plan is realistic and being followed Steve Montgomery at Ten Six has published a free eBook, An Introduction to the DCMA 14-Point Assessment, and I find it particularly well done. Each point is shown in Primavera P6 with practical examples, along with what to avoid and where to use judgement. No registration needed. https://tensix.com/book-an-introduction-to-the-dcma-14-point-assessment/