User
Write something
Free carpentry webinar is happening in 21 days
Kitchen rip out
3 day process. Day 1 rip out Day 2 first fix plumbing and electrical Day 3 plastering Now we leave it for 2-3 days until the plaster is pretty much dry before we start fitting units or painting. Painting is best done before the units are in but being on a tight schedule normally means fitting some units while the plaster is only just dry but not dry enough for paint. Sometimes the painter will come in and give the walls a base coat while covering the units with dust sheets.
0
0
Kitchen rip out
1-30 of 44
Wayne’s Carpentry World
skool.com/wayne-lees-carpentry-school-1929
British Carpentry Coaching
This channel bridge’s the gap between learning through videos and learning on the job through webinars and consultations
Powered by